Miscellaneous metals

Miscellaneous metals estimating: Division 5 without the scope gaps.

Stairs, guardrail, ladders, grating, embeds, bollards. That's the 05 50 00 work a general contractor assumes somebody else already carried. Send a PDF plan set; get the whole bid package back in 24–48 hours. Every line traces back to a sheet.

Where structural steel ends and miscellaneous metals begins

MasterFormat draws the line at the section number. Structural steel framing is 05 12 00: beams, columns, braces and base plates, the steel that holds the building up. Metal fabrications is 05 50 00: stairs, railings, ladders, grating, floor plate, bollards, lintels, dunnage, the loose pieces that make it usable. Ornamental work moves again, to 05 70 00.

A general contractor doesn't buy it that way. They buy Division 5, from two different subs, and assume the two bids meet in the middle.

The items in the gap are always the same. Loose lintels over masonry openings, drawn on the architectural sheets and priced by nobody. Roof-screen and equipment support steel — dunnage — detailed on an S sheet, read as structural by the misc shop and as misc by the structural fab. Stair support steel: the beam that catches the top landing, which the structural set hands off as by stair supplier while the stair details say steel by others. Slab-edge angles, pipe guards, elevator divider beams, trench frames.

The scope gap is not in either bid.

It lives between them, invisible until buyout, and then belongs to whichever sub wrote the vaguer exclusion. Read the spec's section list, then name the section you're not carrying. One line, and it saves the job.

Stairs and landings: count risers, not linear feet

A stair is the item most often taken off wrong, because it prices as a count and measures like a length.

Read the stair section, not the plan. A 12'-8" floor-to-floor at 7-1/4" risers is 21 risers, and 21 risers rarely fits one straight run. It lands as two flights and an intermediate landing. The landing is a separate fabrication, with its own channel frame, pan and connections. Counting one stair per floor loses half the work.

The flights ride on a pair of channel stringers, usually MC12×10.6. The stringer is sized by the span between landings, not the riser count. Split the flight and the stringer gets shorter: a different piece, not the same piece measured twice.

Then the tread. A metal pan tread is a formed pan filled with concrete by somebody else, and the fill note decides who. Bar-grating treads with a nosing are a different unit price and lead time.

The guard is where the money leaks. The rail along the open side of a flight and its landings usually rides with the stair. The guard at the floor opening often does not: it's drawn on the architectural plan rather than the stair sheet, and both subs assume the other has it. The wall-side handrail is a third item. We take all three off separately.

Guardrail, handrail, and the LF-versus-each problem

A rail quantity in linear feet is half a takeoff.

The linear feet buy tube or pipe; everything expensive is a count. Posts carry the concentrated load, so they set the spacing: roughly 4'-0" to 6'-0" on center for a picket guard, tighter for cable, where tension pulls the end posts hard enough to change their size. Then the infill: picket at 4 inches clear, glass that pulls Division 8 into your scope, or cable.

Two runs can measure the same 60 linear feet and be nowhere near the same price, so the workbook carries each part of a rail separately.

Guardrail, 42 in
Open sides of floors, landings, mezzanines and stair flights.LF + EA posts
Wall-mounted handrail
One each side on a stair, 1-1/2 in Schedule 40 pipe unless the schedule says otherwise. Brackets at 4'-0" on center, one within a foot of each end.LF + EA brackets
Returns and terminations
Every rail returns to a wall or a post. Each is a fitting, a joint and a finish operation.EA
Post base connection
Welded base plate, cored sleeve with grout, or a side-mounted fascia bracket. Three different prices.EA

Ladders, grating, floor plate and bollards

This is the work a GC calls the small stuff and a fab shop knows is half its hours.

Fixed ladders
Rung or side-rail, with walk-through extensions 42 in above the landing. Cages are no longer the default on new work. Check whether the spec calls for a ladder safety system.EA + VLF
Ship's ladders
50 to 70 degrees, with their own handrail and landing detail. Not a stair, not priced like one.EA
Roof hatches and safety posts
The hatch is usually not yours. The ladder below it, the safety post and the curb angle are.EA
Bar and plank grating
19-W-4 bar grating on 1-1/4 × 3/16 bearing bars, plank, or serrated safety grating. Every cutout, band and hold-down clip is labor that square footage won't catch.SF + EA cutouts
Trench and pit covers
The angle frame (L3×3×1/4 and up, with anchors) is a separate fabrication from the cover, and normally set by the concrete sub.LF frame + EA cover
Floor plate
Checkered plate over a frame. Deflection sets the thickness, not strength.SF
Bollards and pipe guards
Fixed or removable, filled or hollow, capped or sleeved. Each variation is its own line; the footing is not yours.EA

Embeds, anchor bolts, and who sets them

Three verbs decide this scope and they're not synonyms: furnished by, installed by, set by.

The AISC Code of Standard Practice sets the default: the rods are the fabricator's to furnish, along with the embedment drawing that locates them, and somebody else sets them in the formwork. It's the most common place a metals bid and a concrete bid fail to touch. Embed plates for stair landings, rail posts at a slab edge and equipment supports sit in the same crack.

So we write it out item by item, before the GC decides for you. Neither column is a rule; say which default you took.

Carried in the metals package

  • Anchor rods, nuts, washers and setting templates, furnished loose
  • Embed plates, weld studs and deformed bar anchors shown in the details
  • Loose lintels and bearing plates scheduled in Division 5
  • Rail post sleeves and stair landing embeds, ahead of the pour
  • Shop primer per the finish schedule

Excluded, in writing

  • Setting embeds and anchor rods in the formwork
  • Layout and survey of the anchor bolt pattern
  • Non-shrink grout under base plates
  • Coring, cutting and patching of finished concrete
  • Firestopping at floor and shaft penetrations

Elevator and shaft steel

Hoistway steel is a small quantity that can hurt you, because you bid it before the drawings exist: the elevator supplier's shop drawings arrive after buyout, carrying the loads and dimensions your steel has to match.

Normally in the metals package: divider beams between hoistways, the hoist beam at the top of the shaft with its capacity tagged, sill angles at every landing, backing steel at the rail brackets where the shaft is CMU or metal stud, the pit ladder and sump grate.

Normally not: the guide rails and their brackets, the cab, the hoistway door frames and the toe guards. Those ride with the elevator contract, in Division 14.

So carry the steel you can see, state the hoist-beam capacity and landing count you assumed, and put the question in writing. That RFI comes drafted in the package.

How we split the scope on your proposal

Every package states scope by section number, item by item, on the face of the proposal: what you carry, what you exclude, and what you carry furnish-only. Furnish-only matters more in misc metals than anywhere else, because it's the right call for embeds and anchor rods.

Each quantity in the workbook carries the sheet it came from: a rail run says A4.02, a grating quantity says S3.1. That pays twice: while you're pricing, and after you win, when the GC asks why a change order is a change order.

Your logo, your rates, your language. Excel, Word and PDF, all editable. Nothing goes to a GC that you haven't read first.

What it costs

Your first metals package is free. No card, no contract.

After that it's per bid package: Starter $299–399 for small scopes, Standard $549–899 for a typical commercial bid, and Complex $1,200–2,500 for large or multi-building work. Add 35% for a 24-hour rush; standard turnaround is 24–48 hours.

We work from offices in San Jose and San Diego, and take plan sets from every county in the state — out of state too. Your plans are never shared, never used to bid against you, and deleted on request.

Structural steel and miscellaneous metals, CSI Division 5, and concrete, CSI Division 3, are live today. Framing, drywall, mechanical, plumbing and electrical are in development; each goes live when every quantity it produces can name the sheet it came from. If your scope is beams and columns, start with structural steel estimating; if it is footings and decks, start with concrete estimating.